18.09.2019: Status Report from NLI Project Team at Preem Lysekil

During the REV19 audit shutdown at Preem Lysekil, NLI holds two contracts – Amin Piping and Reaktor Work. In total, NLI engage 65 people at the audit shutdown project that started 6th september 2019, and will be finished ultimo October. So far our work performance are well proceeding, and the customer is satisfied with our HSE focus and also the quality of our deliveries. Preem Lysekil conducts Audit Shutdowns every 6 years, and there are up to 2,500 people throughout the facility on projects and maintenance work.

Picture text:
A joyful NLI Project Team, from the bottom of stairs: Dag Tore Johnsen, Jarle Sivertsen, Martin R Hansen, Trond Wiklund, Daniel Johnsen, Ronny Hermundsli og Roger Robertsen

HSE NEWS Preem REV-19_02.10.2019

Contact: Dag Tore Johnsen, Project Manager